Capital requests for fiscal year 2028 are being drafted this fall at many health systems, well before the money is available to spend. A facility director who arrives at that process with a list of aging equipment and a general warning about deferred maintenance will lose to the project with a revenue projection. The aim is to turn a list of old equipment into a risk statement that a finance committee can rank next to a new service line.
The market the request enters
Rating agency data show that capital spending is rising but that it is not primarily going to the physical plant. HFMA’s reporting of Fitch Ratings medians for not-for-profit hospitals and health systems puts capital expenditures at 123.4 percent of depreciation in fiscal 2024, and at 142.7 percent in fiscal 2025, the highest since 154.4 percent in fiscal 2008. The same reporting describes average age of plant at 12.7 years, up from 9.8 years in fiscal 2004. HFMA’s two articles attach the 12.7 figure to different fiscal years, so check Fitch’s published medians before quoting a year. Fitch’s drivers of capital spending include capacity shortages, ambulatory expansion, and AI and digital investment, with aging plant and deferred maintenance described as routine needs.
The financing backdrop is uneven. Kaufman Hall reporting summarized by Advisory Board put calendar year-to-date operating margin index at 2.5 percent through June 2026, down about 6 percent from the first half of 2025, and Fitch’s 2026 outlook said Medicaid reductions in the 2025 federal budget law are expected to hamper margin recovery. Most reductions take effect after 2026, and state-directed payments begin to step down in 2028, which is the first year of the plan being drafted now. Treat that as context for a cautious finance committee rather than a forecast of any one system’s budget.
The implication for a facility team is practical. Infrastructure renewal rarely generates revenue, so it has to be justified through avoided loss and regulatory exposure, and the request needs to be quantified.
Convert condition into risk
Start with a current facility condition assessment
A facility condition index (FCI) compares the cost of deferred maintenance to the replacement value of an asset, and it is usually computed building by building. Published bands vary: one study guide labels below 0.05 as good and above 0.30 as critical, while a vendor guide treats values above 0.10 as needing intervention. Confirm which scale your board uses before comparing portfolios, and say which scale you used in the request. An assessment more than a few years old will not survive a finance committee’s questions, so update the data for the systems that carry the greatest consequence. Our facility condition assessment overview covers the method.
Rank by consequence, not age
NFPA 99 sorts building systems into risk categories according to the consequence of failure, with Category 1 covering systems whose failure is likely to cause major injury or death. That taxonomy gives you a defensible ordering for a request. A 30-year-old air handler serving an operating room belongs ahead of an older but low-consequence system, and the rationale is already in a code your surveyors know.
For each candidate, write four lines:
- What the asset does and which services depend on it.
- What fails if it stops, in clinical and regulatory terms.
- What the evidence is (work order history, failed tests, parts availability, assessment scores).
- What the alternatives cost, including the cost of doing nothing.
A formal, documented risk methodology with defined rating levels is also what auditors look for in capital prioritization processes in other sectors. The principle carries over: a request that shows how it was ranked is easier to approve than one that asks for trust.
Make the regulatory exposure explicit
Several infrastructure categories connect directly to survey and Conditions of Participation requirements: emergency power, ventilation and pressure relationships, water systems, life safety components, and medical gas. State the requirement and the citation that applies. For example, a generator that cannot meet its testing and load requirements is a regulatory problem as well as an equipment problem, and the NFPA 110 testing guide lays out the obligations. Accreditation 360 consolidated the Environment of Care and Life Safety chapters into a single Physical Environment chapter in 2026, so a single request can reference one chapter for a cluster of building systems.
Do not overclaim. A request that says a project is required by code when it is only advisable will be challenged, and the next request loses credibility.
Sequence the request around availability
Equipment lead times and installation constraints shape what can happen in a fiscal year, so a capital plan that ignores them will carry money forward unspent. Build the request with these in mind:
- Outage windows. Replacing electrical or HVAC equipment in a hospital needs a phased plan that keeps services running, which may stretch a project across two fiscal years.
- Procurement timing. Long-lead equipment may need a deposit or a purchase order in the prior year to arrive on time.
- Design lead time. Engineering for a central plant or electrical distribution project must precede the construction request.
Our predictive maintenance business case piece describes how condition data supports the replacement timing argument.
Present options, not a single ask
Finance committees prefer choices. Offer three tiers for the major items: a minimum scope that eliminates the highest-consequence risks, a recommended scope that bundles related systems to share construction cost, and an extended scope that adds efficiency or capacity. Show the cost and the residual risk for each. If the committee funds only the minimum, it will know which risks remain and who accepted them, and that record becomes useful at the next cycle.
Include the operating side. Maintenance cost on failing equipment is a real number. Where replacement lowers energy use or service calls, estimate it from your own utility and work order data and label it as an estimate.
Common errors in infrastructure requests
- Using one overall deferred maintenance total with no breakdown by system or consequence.
- Quoting industry statistics without the source or the fiscal year.
- Presenting every project as urgent, which leaves the committee to pick.
- Leaving out the staffing and outage plan that execution needs.
- Ignoring how the request interacts with technology and growth projects that share the same electrical, cooling, and space capacity.
That last point is easy to miss. New imaging, digital infrastructure, and ambulatory expansion all draw on the same plant. A facilities request that shows how its projects enable those priorities, such as adding cooling capacity ahead of equipment installation, is a partner to the growth plan rather than a competitor.
What to do before the submission deadline
Pull the current assessment and update the consequential systems. Rank them by consequence with the evidence attached. Write the three-tier option set. Schedule time with finance before the formal submission so the numbers and assumptions are tested while there is still time to revise.